Swansea Free Public Library


CONSTRUCTION UPDATE - MARCH 5, 2025

  • New Addition Exterior

    • Masonry work has begun, progressing from east to north to west.

    • Roofers progressing on AVB and underlayment with improved weather.

    • Eaves installed along the new addition roof.

    • Building is 99% weather tight.

    • Window testing performed on 2/26; awaiting final report.

  • New Addition Interior

    • MEP (Mechanical, Electrical, Plumbing) rough-ins progressing on both floors.

    • Fireproofing completed on interior and exterior steel.

    • Interior metal framing completed.

    • Ceiling soffits being installed on the first floor.

  • Existing Library

    • MEP rough-ins progressing in the attic and first floor.

    • Sump pump installed and backfilled in basement.

    • Electrical switchgear delivered and installed in basement.

  • Site Work

    • Retaining wall along the driveway completed.

 

CONSTRUCTION UPDATE - JANUARY 31, 2025

  • Window Installation Completed

  • Air Vapor Barrier of sides completed, AVB on roof is ongoing

  • Interior framing nearly complete

  • Main stair and emergency stair pans poured

  • Retaining wall work ongoing

  • Interior mechanical roughs are starting up on the interior

  • Soffit work ongoing

  • Exterior masonry work has begun

  • Transformer delivered and installed

 

CONSTRUCTION UPDATE - DECEMBER 23, 2024

  • The 2nd floor deck and 1st floor slab have been poured

  • Exterior framing of the 1st and 2nd floor have been completed.

  • Sheathing of the exterior is nearly complete

  • Inground electrical boxes on the first floor have been installed

  • Electrical conduit continues to be installed in the existing building

  • Window installation began on 12/23

  • A column signing was held

 

CONSTRUCTION UPDATE - NOVEMBER 27, 2024

  • Steel for the new addition has been erected, and steel decking is complete

  • Water main has been installed in the driveway

  • Underground electrical conduits have been installed and backfilled

  • Exterior metal framing of the first floor in the new addition is underway

  • Town Hall septic system has been installed

  • Additional trenches for septic field have been completed

 

CONSTRUCTION UPDATE - OCTOBER 24, 2024

  • Underground plumbing backfilled in new addition

  • Primary and Secondary Electrical Conduits installed

  • Temporary framing installed in opening in former periodicals room

  • Forced sewer main and electrical to rear of site installed and backfilled

  • Steel erection began on October 15th and is ongoing

 

CONSTRUCTION UPDATE - SEPTEMBER 20, 2024

  • Footings completed and foundations completed

  • Waterproofing around new foundations complete

  • Masonry for elevator shaft complete

  • Began underground utility work at both the site driveway and the new addition

  • Ongoing compaction of the backfill at the addition

  • New attic insulation installed in existing building

  • Underground plumbing work ongoing in existing building


CONSTRUCTION UPDATE - AUGUST 21, 2024

  • Back parking lot area backfilled

  • Footings completed and foundations nearly complete

  • Waterproofing and CMU infill at existing building complete

  • Existing shelving removed to prepare for connection to addition

  • Began geofoam installation at junction of new and existing building


CONSTRUCTION UPDATE - JULY 24, 2024

  • Site drainage and septic system installed

  • Continuing to backfill and establish grades in back parking lot area

  • Excavation for footings and foundations completed

  • Compaction testing for footings and foundations completed

  • Footings formed and rebar installed

  • Began pouring footings


Construction Update - June 24, 2024

  • The general contractor, Delphi Construction, has mobilized on-site

  • Site fencing and protection was installed

  • A Groundbreaking Ceremony was held on June 1st, 2024

  • Work in the back parking lot began for site drainage and the septic system

  • Abatement was performed in the 1960’s addition to prepare for demolition

  • Additional abatement was performed in the 1890’s portion of the building

  • The 1960’s addition was demolished

  • Site preparation for foundations has begun for the new portion of the building


Groundbreaking Ceremony - June 1, 2024

 

The Swansea Free Public Library broke ground on June 1, 2024! The ceremony took place outside the historic library, with members of the select board, library committee, and library staff members present to commemorate the renovation and expansion project!